It has been a busy couple of months in north Queensland as works progress on the Haughton River Floodplain Upgrade.

The project covers essential upgrades to the Bruce Highway, designed to improve safety and efficiency for road users, as well as significantly improving flood immunity.

Bielby Managing Director, Adam Edwards recently visited the site, “It was great to see such impressive progress being made on the project, with significant works being undertaken in recent months. All credit must go to everyone involved in the joint venture team.”

But, as with any project, milestones achieved don’t mean resting on laurels! Throughout November, the project will continue at a rapid pace which will see the completion of key bridges, critical traffic switches and culvert installation at the project’s northern end.

As the project moves through its next phase, we look forward to bringing you updates on the following works:

  • Construction of main deck spans at the Upper Haughton/Hodal Road overpass and Pink Lily Lagoon bridge
  • installation of flood-prone culverts at the northern end of the project
  • erection of final super T girders at the Haughton River bridge and completion of bridge substructure construction
  • completion of the Horseshoe Lagoon bridge
  • switch Bruce Highway traffic onto the new, final alignment south of Trembath Road
  • complete pavement rehabilitation on overtaking lanes (between Shirbourne Road and Woodstock Giru Road).

For more information on Bielby’s involvement, please visit: https://www.bielby.com.au/haughton-river-floodplain-upgrade-project/

About the Project

The $513 million project is jointly funded by the Australian Government ($414.4 million) and Queensland Government ($102.9 million). The project covers essential upgrades to the Bruce Highway, designed to improve safety and efficiency for road users, as well as significantly improving flood immunity. The project is being delivered by The Infrastructure Group (TIG), a joint venture between Bielby, BMD Constructions, JF Hull Holdings and Albem Operations, on behalf of the Department of Transport and Main Roads.